Warren's K-8 enrollment is up 10 percent in five years, and the plan on the table is a grades 4 and 5 school

Warren K-8 enrollment rose from 1,537 to 1,692 in five years and is projected at 1,980 by 2031. The board votes September 28 on a grades 4 and 5 school.

Share
Bar chart of Warren Township K-8 enrollment, 1,537 in 2020-21 rising to a projected 1,980 by 2031.
RecordThe primary document, reported. What the labels mean

This story updates the school decisions tracker, the running file that carries the current status.

The short answer

Warren Township's K-8 district has a recommendation on the table to reorganize its elementary schools. Enrollment rose from 1,537 students in 2020-21 to 1,692 in 2025-26, and from a 2026 planning baseline of 1,712 the district projects 1,980 students by 2031 once natural growth and Round 3 housing are counted. The Board of Education's ad hoc committee recommends an Intermediate School Model: three kindergarten through grade 3 schools, one school for grades 4 and 5, and Warren Middle School unchanged at grades 6 through 8. The anticipated board vote is September 28, with implementation targeted for 2027-28. The report carries no cost estimate.

Map of Warren Middle School at 100 Old Stirling Road in Warren Township, New Jersey, with the location marked.
Warren Middle School, 100 Old Stirling Road. The board meets here on August 31 and September 28. Open in Google Maps. Map data © OpenStreetMap contributors.
1,712
K-8 students, 2026 planning baseline
1,980
Projected by 2031 with Round 3 housing
Sep 28
Anticipated board vote
2027-28
Target implementation year

What the report recommends

The Planning for Growth Final Report and Recommendation, dated June 2026, recommends what the district calls the Intermediate School Model. Today Warren runs four elementary schools covering kindergarten through grade 5, plus Warren Middle School for grades 6 through 8. Under the recommendation, three buildings would run kindergarten through grade 3 and one building would hold grades 4 and 5 for the whole township.

LevelTodayUnder the recommendation
ElementaryFour schools, kindergarten through grade 5Three schools, kindergarten through grade 3
IntermediateNoneOne school, grades 4 and 5
MiddleWarren Middle School, grades 6 through 8Warren Middle School, grades 6 through 8, unchanged

The report does not name which of the four buildings would become the grades 4 and 5 school. It also leaves one structural question open, whether the district's existing preschool program would sit in one school or be spread across the three kindergarten through grade 3 schools.

The enrollment numbers

YearStudentsBasis
2020-211,537Actual
2025-261,692Actual
20261,712Planning baseline
20311,980Projected, natural growth plus Round 3 housing
20312,173Round 4 stress test scenario

From 1,537 to 1,692 is 155 students in five years, or 10.1 percent. From the 1,712 baseline to 1,980 is another 268 students, 15.7 percent. The 2,173 figure is not a forecast. The report treats a full Round 4 build as a stress test, a way of asking what the buildings would have to absorb at the high end.

Two figures in circulation are close but not identical. The district's advertised K-8 enrollment for 2026-27 is about 1,734, which is the budget document's number. The 1,712 in this report is the planning baseline the projection model runs from. They are not the same measure and should not be swapped for each other.

The pressure is not spread evenly

The report is direct that the problem is distribution, not just totals. In its words, "Central School is projected to remain space-constrained, and Woodland School is projected to experience significant growth as remaining Round 3 housing is absorbed."

It also pushes back on a simple room count. Available space is not the same as usable space, the report argues, because many rooms already carry intervention, related services, special education, preschool, multilingual learner support, enrichment, small group instruction and district operations.

Housing is inside the projection

Round 3 and Round 4 are affordable housing obligation rounds, and both appear throughout the enrollment model. The report says housing development and natural enrollment patterns create more significant pressure in some attendance zones than others. That is the same machinery covered here in the four affordable housing districts Warren created in 2026 and in the development pipeline table.

Two members of the Township Committee, Daniel Croson and Vanessa Kian, sat in the working group, which is the point where township land use and school capacity meet in the same room. The zoning side of that is on the zoning and development page.

The dates

DateWhat happensWhere
June 15, 2026Public board presentation of the final report and recommendationAlready held
July 20, 2026Board goal setting, Planning for Growth named the district priority for 2026-27Already held
August 31, 2026Board meeting update on the refined model and the decision pathwayWarren Middle School, 6:30 p.m.
September 28, 2026Anticipated board vote on the Intermediate School ModelWarren Middle School, 6:30 p.m.
2027-28 school yearTarget implementation, contingent on board approvalDistrict wide

August 31 is a staff development day, so the K-8 schools are closed to students that day and the board meets that evening. The K-8 year itself starts September 2, a week after Watchung Hills, which is the two calendars problem Warren households are living with right now. Both board dates are on the Warren calendar.

What I could not verify

The report contains no cost estimate, no funding plan and no referendum proposal. It says preliminary staffing and financial implications should be developed before the board vote, but those numbers are not in this document. I also could not find published functional capacity figures per building, or the name of the firm that produced the enrollment projection and utilization study. The district's Planning for Growth FAQ is hosted on a Google Sites page that would not open for me, so its contents are not reflected here. If the district publishes staffing, cost or capacity figures before September 28, this post will be updated.

For context on what Warren voters have already approved, a March 2025 facilities referendum of $8.5 million passed with $3.4 million in state funding, presented as no tax impact. That is covered on the Warren schools page, along with the two district structure and how each district lands on your property tax bill.

Author's note

This section is my opinion, kept separate from the record above. A grade reorganization is the least expensive of the structural options, because it moves children rather than building rooms. That is exactly why the missing cost and staffing figures matter before September 28 rather than after. Transportation changes, class size effects and what happens to the preschool program are the three things I would want quantified in the August 31 update. Warren has been adding housing for several years, and this is the first time the school side has put a structural answer in writing.

If you are buying into a specific elementary zone, note that zone assignments are set by the district and can change. Confirm any assignment with the district office rather than relying on a listing.

Sources
  1. Warren Township Schools, Planning for Growth Final Report and Recommendation, June 2026. https://www.warrentboe.org/pdf/planningforgrowth/Planning%20for%20Growth%20Final%20Report%20-%20June%202026.pdf
  2. Warren Township Schools, Planning for Growth hub. https://www.warrentboe.org/planningforgrowth/
  3. Warren Township Schools, Planning for Growth 2025-2026 meeting materials. https://www.warrentboe.org/planningforgrowth/2025-2026
  4. Warren Township Schools, Demographic Study Key Findings and Planning Guardrails. https://www.warrentboe.org/pdf/planningforgrowth/Demographic%20Study%20Key%20Findings%20and%20Planning%20Guardrails.pdf
  5. Warren Township Board of Education, 2026 meeting schedule and membership. https://www.warrentboe.org/board/
  6. Warren Middle School, 100 Old Stirling Road. https://www.warrentboe.org/schools/middle/
  7. Warren Township Schools, Planning for Growth FAQ, which would not open at the time of writing. https://sites.google.com/warrentboe.org/planningforgrowthfaq/home
John Mangini

John Mangini

Broker / Owner, NextHome Premier

Warren Township resident and full time broker, licensed in New Jersey since 2002. Warren, Local. is written from live Garden State MLS data, township records and primary sources. Every figure is traceable to a source listed above.